On October 23, the domestically-produced high-speed high-speed natural gas compressor RTY3360 successfully completed the no-load commissioning at the Shapingchang booster station in the Liangping work area of ​​the Southwest Oil and Gas Field.
This compressor group was hoisted to the site in June last year, hoisted in place in December, completed installation in May of this year, and accepted mid-September in mid-September. In more than one month, after the rectification of the problem, the purging, replacement, boosting, leak testing, and joint debugging of the unit and supporting pipelines, the unit successfully completed no-load and small-cycle debugging of the unit, which created a good test for the unit's loading and operation. condition.