Anqing Petrochemical on the 4th by the end of the pump overhaul
Starting on March 13, 2014, Anqing Petrochemical Ministry of Thermoelectricity No. 4 on the water pump overhaul work after 36 days, successfully completed the overhaul task on April 19, started operation on April 20, achieving a successful goal after overhaul.
Anqing Petrochemical Thermoelectricity Jiangbian No. 4 pump overhaul, the planned duration of 40 days, the main task of the follow-up pump motor dismantling overhaul, follow the pump main body dismantling overhaul, follow the pump casing flow path wall anti-corrosion treatment, suction cabin dredging and other work , By Anhui Yingchuang 4 branch companies to undertake the major tasks of this major repair. The pump has been dismantled and overhauled for 10 years, and there are many problems with equipment defects. The Ministry of Thermoelectricity seriously organized the joint efforts of Anhui Yingchuang Seishi 4 Branch Company and the electrician maintenance personnel of the Ministry to overcome the narrowness of the pumping house's maintenance site and the difficulty of overhauling. The No. 4 and No. Many difficulties, reasonable deployment of manpower, overtime work, safe and efficient completion of this overhaul task, and to achieve a successful goal of driving after No. 4 pump overhaul.
Through nearly 48 hours of operation observation, No. 4 pump performance indicators meet the requirements of equipment output, and solve the long-term bottleneck of No. 4 circulation motor coil operating temperature, running noise, insufficient pump output, can not meet production needs, For Anqing branch power supply and heating system security and stability, to ensure production safety, and provide a solid guarantee of equipment.
Eye Grab Hook,Galvanized Hook,Eye Slip Hook
Yangzhou Jieerte Steel Cable Co., Ltd , https://www.yzwirerope.com